Company Preferences - Production

Production

Under the Production Section of your Company Preference, you can edit specific settings pertaining to your work order in the Production stage. By selecting some of the choices under this company preference, you can control how the components on your work order are processed and how work order instruction will be passed on to the production floor. 

You can set up the following work order options:

  • Enable Splitting.   When you want to Finish a work order partially,  you can finish the work order while creating a 2nd work order for the remaining quantity.
  • Enable Drill Down:   When you want to create work orders for sub-assemblies within a work order.
  • Enable Flatten:  When you want to remove the BOM structure of 'Phantom BOMs' and show only the components on the work order. 

Click Save when done.